Risk Register
Ris
k ID Risk Statement Probability Impact Risk Rating Opportunit y or Threat EMV Cost (Cost *
Pr
...[Show More]
PROJECT RISKS AND ISSUES MANAGEMENT
This study source was downloaded by 100000851682045 from CourseHero.com on 10-21-2022 00:52:05 GMT -05:00
https://www.coursehero.com/file/64877449/Risk-registerdocx/
INDIVIDUAL ASSIGNMENT 1 2
Risk Register
Ris
k ID Risk Statement Probability Impact Risk Rating Opportunit y or Threat EMV Cost (Cost *
Probability)
EMV Duration in
Days (5 working
days in a week)
Related
Solution
1
Top Two employees
quitting the company.
Causing a month delay
to the project and
additional cost of
$5000.
80% 4 High Threat 5000 * 80%
= - $4,000
(20 working days
in a month)
20 * 80%
= 16 days
Solution 1,
Scenario d
[Show Less]